| Name | IAIS Iowa River Bridge Chicago, Rock Island & Pacific Railroad Bridge #2371 |
| Built By | Chicago, Rock Island & Pacific Railway |
| Currently Owned By | Iowa Interstate Railroad |
| Superstructure Contractor | American Bridge Company of New York (Lassig Plant) Bethlehem Steel Company of Bethlehem, Pennsylvania (Span #3) |
| Substructure Builder | Chicago, Rock Island & Pacific Railway Company Forces Unknown (West Abutment) |
| Length | 645 Feet Total, 78 Foot Largest Span |
| Width | 1 Track, Substructures Built For 2 Tracks |
| Height Above Ground | 40 Feet (Estimated) |
| Superstructure Design | Deck Plate Girder and Concrete Modular Girder |
| Substructure Design | Concrete and Steel Pile |
| Date Built | 1901, Span #3 Replaced 1949; East Approach Replaced 2023 |
| Traffic Count | 5 Trains/Day (Estimated) |
| Current Status | In Use |
| Chicago, Rock Island & Pacific Railroad Bridge Number | 2371 |
| Iowa Interstate Railroad Bridge Number | 237.10 |
| Significance | Local Significance |
| Documentation Date | 9/10/2017 |
In 1856, the Mississippi and Missouri Rail Road Company (M&M) constructed 55 miles of new railroad, extending from Davenport, Iowa to Iowa City, Iowa. As part of the work, a wooden bridge was constructed across the Mississippi River, connecting Rock Island, Illinois and Davenport. In 1862, the line was extended an additional 31 miles to Marengo, Iowa; followed by an additional 20 miles to Brooklyn, Iowa in 1863 and 26 miles to Kellogg, Iowa in 1864. In 1866, the M&M and the Chicago and Rock Island Rail Road Company (C&RI) merged to form the Chicago, Rock Island & Pacific Railroad (Rock Island), which constructed an additional 44 miles to Des Moines, Iowa in 1867. In 1869, the line would continue to be extended west towards the Missouri River. At Davenport, this line connected to an existing Rock Island line, which extended east to Chicago, Illinois. In 1880, the Rock Island was reorganized as the Chicago, Rock Island & Pacific Railway. The Rock Island constructed and acquired a large network of railroads, primarily in Iowa during the late 1880s. This line became part of the principal mainline of the Rock Island, and allowed for further development of branch lines throughout central Iowa and eventual expansion west of the Missouri River.
In the late 19th Century, several improvements were made to the line, including revising grades, curves and replacing wooden bridges with stone and iron structures. Due to heavy traffic over this line, portions of the line between Davenport and West Liberty was double tracked in the late 1890s. The Rock Island struggled financially throughout much of its history, experiencing repeated bankruptcies and chronic instability. After World War II, the Rock Island struggled to survive, proposing mergers and deferring maintenance on their routes. The railroad reorganized as the Chicago, Rock Island & Pacific Railroad in 1948. By the mid-1970s, the railroad was in serious decline. The railroad secured loans to eliminate slow orders, acquired new equipment, and attempted to restore profitability. Several sections of this line had fallen into serious disrepair, hampering the Rock Islands ability to maintain efficient operations. In 1978, the railroad came close to profit, but creditors were lobbying for a complete shutdown of the Rock Island. During the fall of 1979, a strike crippled the railroad, and by January of 1980, the entire system was ordered to be shut down and liquidated. Many of the lines and equipment were scrapped. Profitable sections of railroad were prepared for sale.
In November 1981, the Iowa Railroad Company (IARR) began operations over the former Rock Island mainline in western Iowa. In June 1982, the IARR entered into a two-year lease for the entire Rock Island mainline between Bureau, Illinois and Council Bluffs, Iowa; including the Davenport to Des Moines section. In 1983, concerns had grown over the ability of the IARR to provide reliable service to shippers along the line, and several industries came together to form Heartland Rail Corporation, which purchased the line between Bureau and Council Bluffs from the Rock Island trustees. Iowa Interstate Railroad (IAIS) was chosen to operate the line, and began operations in late 1984. After years of thin profit margins, IAIS began making significant financial strides in the 1990s and early 2000s, eventually becoming a major railroad in central Iowa. Increased profit margins and large grants meant IAIS could rebuild deteriorated track, improve bridges and expand operations. Today, IAIS continues to operate the Iowa City Subdivision between Davenport and South Amana, as well as the Newton Subdivision between South Amana and Des Moines.
Located in downtown Iowa City, this large deck plate girder bridge carries a former Chicago, Rock Island & Pacific Railroad (Rock Island) mainline over the Iowa River, Cedar Rapids & Iowa City Railway and US Highway 6. The first bridge at this location was likely a timber deck truss bridge, constructed when the line was first built. This bridge apparently had lengthy timber pile trestle approaches at either end, which spanned numerous streets and Ralston Creek. In 1869-1870, the Rock Island completed a major improvement project in Iowa City, filling the lengthy timber approaches. The Iowa River bridge was also reconstructed at this time with new stone piers and abutments, likely retaining the wooden deck truss design. In 1881, a new iron bridge was completed at this location. This bridge consisted of two 155-foot and one 152-foot pin-connected Pratt deck truss spans, approached by lengthy iron deck plate girder viaducts on either end. Between 1899 and 1902, the Rock Island invested significant capital into this line, replacing aging bridges with new steel and concrete structures. In 1901, the bridge was reconstructed with eight deck plate girder spans on new concrete substructures, and large portions of the viaduct approaches were filled. It is unclear if any portions of the previous bridge were reused, although a bridge in Estherville, Iowa potentially reused portions of the truss spans. When the new bridge was constructed, the substructures were constructed so that a second track could be added in the future, although this plan never came to fruition. In 1949, the bridge underwent a significant rehabilitation, including the addition of a timber pile trestle approach at the east end, the complete replacement of span #3 and the general rehabilitation to the remaining girder spans. Reportedly, the original span #3 was reused at an undisclosed location. The most recent alteration to the bridge came in 2023, when the timber pile trestle approach was replaced by concrete modular girder spans, giving the bridge its present configuration.
Currently, the bridge consists of two 78-foot, four 74-foot and two 70-foot deck plate girder spans, approached by two concrete modular girder spans on the east end. Almost the entire bridge is set onto concrete substructures, except for the east approach which is set onto steel pile bents. The main spans of the bridge use a standard design, consisting of two heavy plate girders and an open deck. The 1949-era span #3 is almost identical to the remaining spans, except for the steel is likely a different grade material and a longitudinal bracing is configured slightly different. All of the main piers use a standard rectangular design, which are likely founded on timber piles. It is unclear if any portions of the previous bridge were reused in the present substructure. The west abutment uses a standard design with sloped wing walls, and appears to have been constructed at a later date than the remaining substructures. The easternmost pier was originally the east abutment, and uses a stepped wing wall design with a demolished backwall. It is unclear why the east approach was added, although it was likely to improve erosion around the east end of the bridge. American Bridge Company fabricated most of the spans at their Lassig Plant in Chicago; while Bethlehem Steel Company fabricated span #3. It is believed that the piers were all constructed by railroad company forces, while it is unknown if the west abutment was constructed by railroad company forces or by an unknown contractor. The 1949 rehabilitation was carried out by railroad company forces, which removed, repaired and re-erected most of the spans. Deck plate girder spans were popular for railroad use, as they were durable and easy to construct. Since the initial construction, the bridge has seen minor alterations to the piers, particularly the reinforcement of the bases with sheet piling and concrete. Today, it remains in regular use as part of an Iowa Interstate Railroad mainline. Overall, the bridge appears to be in fair to good condition, with no significant deterioration noted. The author has ranked this bridge as being locally significant, due to the common design.
Citations
| Build date and builder (superstructure) | American Bridge Company plaque |
| Rehabilitation date and builder (span #3) | Iowa City Press-Citizen; July 25, 1949 |
| Railroad History Citation | ICC Valuation Information, Compiled by Richard S. Steele |