RI Branch Little Fourmile Creek Culvert


Click the photo to view the full-size version

1/17
Date Taken:
Author:
Caption:

Name RI Branch Little Fourmile Creek Culvert
Built By Chicago, Rock Island & Pacific Railway
Currently Owned By Iowa Department of Transportation
Contractor Unknown
Length 10 Feet Total
Width 1 Track (37 Feet)
Height Above Ground 10 Feet (Estimated)
Superstructure Design Concrete Arch Culvert
Substructure Design Concrete
Date Built 1896
Traffic Count 0 Trains/Day (Bridge is Abandoned)
Current Status Abandoned
Significance Local Significance
Documentation Date 2/22/2020

In 1853, the Keokuk, Fort Des Moines & Minnesota Railroad (KFDM&M) was organized to construct a new railroad, extending from the Mississippi River at the southeast town of Keokuk, Iowa to Des Moines, Iowa; located near the center of the state.  Grading began in 1855, and track laying commenced the following year.  The first 40 miles were completed between Keokuk and Bentonsport, Iowa by the end of 1857, followed by an additional 36 miles to Ottumwa, Iowa by the end of 1860.  In 1861, an additional 16 miles were completed to Eddyville, Iowa; where work paused due to the Civil War.  Work resumed in 1864, and an additional 23 miles were completed to Pella, Iowa by the end of that year.  The KFDM&M was reorganized as the Des Moines Valley Railroad (DMV) at the end of that year.  In 1865, an additional 14 miles were completed to Monroe, Iowa; and in 1866, the final 33 miles were completed to Des Moines, Iowa.  When the railroad reached Des Moines, it was the first railroad to enter the city.  Work eventually continued northwest from Des Moines.  In 1873, the DMV went bankrupt, and was split into two separate railroads.  The Keokuk & Des Moines Railway (K&DM) was awarded the segment between Keokuk and Des Moines; and the Des Moines & Fort Dodge Railroad (DM&FD) was awarded sections constructed northwest of Des Moines.  

During the 1870s, the Chicago, Rock Island & Pacific Railroad (Rock Island) was rapidly expanding throughout Iowa.  In 1878, the Rock Island secured a lease and began operating the property of the K&DM.  The Rock Island was reorganized as the Chicago, Rock Island & Pacific Railway (Rock Island) in 1880.  The Rock Island operated this route as a secondary mainline, serving industries in southeast Iowa and connecting to other branch lines.  In 1924, the K&DM was merged into the St. Paul & Kansas City Short Line Railroad (StP&KCSL), a Rock Island subsidiary.  The Rock Island struggled financially throughout much of its history, experiencing repeated bankruptcies and chronic instability.  After World War II, the Rock Island struggled to survive, proposing mergers and deferring maintenance on their routes. The railroad reorganized as the Chicago, Rock Island & Pacific Railroad in 1948, and the StP&KCSL was merged into the Rock Island at that time.  Between Oskaloosa and Eddyville, the Minneapolis & St. Louis Railway (M&StL) had operated a parallel line to the Rock Island.  After the M&StL was acquired by the Chicago & North Western Railway (C&NW) in 1960, the C&NW and Rock Island consolidated operations onto one line.  Between Eddyville and Givin, the Rock Island line was maintained and the former M&StL abandoned.  Between Givin and Oskaloosa, the former Rock Island line was abandoned.

By the mid-1970s, the Rock Island was in serious decline.  The railroad secured loans to eliminate slow orders, acquired new equipment, and attempted to restore profitability.  Several sections of this line had fallen into serious disrepair, hampering the Rock Islands ability to maintain efficient operations.  In 1978, the railroad came close to profit, but creditors were lobbying for a complete shutdown of the Rock Island.  During the fall of 1979, a strike crippled the railroad, and by January of 1980, the entire system was ordered to be shut down and liquidated.  Many of the lines and equipment were scrapped.  Profitable sections of railroad were prepared for sale.  The line between Keokuk and Pella was abandoned at the time of shut down.  Iowa Interstate Railroad (IAIS) acquired a short segment between Des Moines and Pella in 1984, and abandoned the Des Moines to Altoona segment in 1986.  In 1995, the C&NW was purchased by Union Pacific Railroad (UP).  In 1998, IAIS abandoned the line between Pella and Otley; followed by the segment between Otley and Prairie City in 2000 and between Prairie City and Mitchellville in 2014.  Today, UP continues to operate a short segment of this line north of Eddyville, while IAIS continues to operate a short segment between Mitchellville and Altoona.  A segment between Monroe and Prairie City has been reused as a trail, while the remainder of the line has been abandoned.



Located on the west side of Altoona, this small concrete arch culvert carries a former Chicago, Rock Island & Pacific Railroad (Rock Island) secondary line over an unnamed creek near the Gay Lea Wilson Trail. The first bridge at this location was likely a timber pile trestle, constructed when the line was first built. In the late 1890s and early 1900s, the Rock Island invested significant capital into this line, replacing aging timber bridges with steel and concrete structures. In 1896, the present concrete culvert was constructed at this location. Currently, the structure consists of a 10-foot by 8-foot concrete arch culvert, set onto concrete substructures and constructed for a single track at a width of 37 feet. The superstructure follows a standard design, with a semicircular arch and medium-sized headwalls. The substructure also follows a standard design, with sloped wing walls which extend perpendicular from the structure. It is unclear if the culvert was constructed by an unknown contractor or by railroad company forces. While concrete arch culverts became popular at the turn of the 20th Century, this culvert is among the earliest all-concrete railroad structures constructed in Iowa. It is unclear why concrete was used for this culvert when stone was still a common building material. It is also unclear if the structure used any reinforcing steel. Since the initial construction, the culvert has seen no significant alterations. After the Rock Island was abandoned, this line was discontinued and all traffic was rerouted onto the parallel mainline. Overall, the culvert is in extremely poor condition, and is likely on the verge of complete failure. A significant portion of the west wall and arch has failed, creating a large hole above the culvert. The author has ranked this culvert as being locally significant, due to the common design.


Citations

Build date Date stamp
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele

Loading...