Name Chicago & North Western Railway Bridge #576
Built By Chicago & North Western Railway
Currently Owned By Wisconsin Department of Natural Resources
Superstructure Contractor Unknown
Length 15 Feet Total
Width 1 Track (120 Feet)
Height Above Ground 10 Feet (Estimated)
Superstructure Design Stone Arch
Substructure Design Stone Masonry
Date Built 1880
Traffic Count 0 Trains/Day (Bridge is Open to Pedestrian Traffic)
Current Status Open to Pedestrian Traffic
Chicago & North Western Railway Bridge Number 576
Significance Local Significance
Documentation Date 7/21/2015

In 1860, the Beloit and Madison Railroad (B&M) constructed 17 miles of railroad, extending from Beloit, Wisconsin to Magnolia, Wisconsin.  In 1864, the B&M constructed an additional 32 miles of railroad, extending from Magnolia to Madison, Wisconsin.  In 1864, the Madison, Lodi and Baraboo Railroad (ML&B) began grading for a new railroad line, extending from Baraboo, Wisconsin to Merrimac, Wisconsin.  The ML&B was acquired by the Baraboo Air Line Railroad (BAL) in 1870, and began construction on a line extending from Reedsburg, Wisconsin to Madison.  In 1870, the La Crosse, Trempealeau and Prescott Railroad (LCT&P) constructed an additional 29 miles of railroad, extending from the Winona & St. Peter Railroad (W&StP) at Winona, Minnesota to the north side of La Crosse, Wisconsin; constructing a large bridge across the Mississippi River.  The BA&L and the B&M were acquired by the Chicago & North Western Railway (C&NW) in 1871.  The C&NW continued construction, eventually opening a 129 mile line between Madison and present-day Medary on the north side of La Crosse in 1873.  This line was difficult to construct, as it crossed through areas of rugged terrain, requiring three tunnels and numerous wooden trestles.  The LCT&P was purchased by the C&NW in 1876.

Soon after completion, this line became an important route for the C&NW.  The line connected an existing mainline to Chicago with the existing W&StP mainline across southern Minnesota.  In addition, the Chicago, St. Paul, Minneapolis & Omaha Railway (Omaha Road, a C&NW subsidiary) mainline ended at this line in Elroy, Wisconsin, providing the C&NW with a connection to the Twin Cities.  Numerous improvements were made in the late 1870s and throughout the 1880s, including filling wooden trestles and replacing wooden bridges with iron and stone.  The C&NW constructed a short 4-mile branch line from Medary to La Crosse in 1886.  By the late 19th Century, traffic over this route had grown to the point that a second track was necessary.  Between 1896 and 1899, the C&NW completed a second track between Evansville, Wisconsin and Elroy.  By the early 20th Century, the C&NW was operating an expansive railroad network throughout the Midwest, radiating north and west from Chicago.  This line initially served as one of the principal mainlines of the railroad, connecting Chicago to the Twin Cities and the mainline to South Dakota.

Between 1910 and 1912, the C&NW undertook a large construction program to construct shorter routes and streamline operations.  A cutoff between Milwaukee and Sparta opened in 1911, reducing the importance of this line.  Between 1953 and 1956, much of the double track would be removed.  A portion of the line was abandoned between Elroy and Sparta in 1964, and became one of the United States first rail-trail projects.  In 1978, the Sparta to Medary and Winona to Trempeleau, Wisconsin segments would be abandoned, followed by the Beloit to Evansville segment in 1979 and the Medary to Trempeleau and La Crosse segments in 1981.  The Reedsburg to Elroy segment was abandoned in 1987.  All of the line west of Reedsburg would be acquired by the Wisconsin Department of Natural Resources for trail use.  

In 1995, the C&NW would be purchased by Union Pacific Railroad (UP).  In 1996, UP leased the Fitchburg to Reedsburg segment to the Wisconsin & Southern Railroad (WSOR).  In addition, UP attempted to abandon the Evansville to Fitchburg segment the same year.  In response to possibly losing railroad service, the communities of Fitchburg and Oregon purchased the line, although it was out of service.  In 2014, the State of Wisconsin acquired the Fitchburg to Reedsburg line, and contionued to lease it to WSOR.  The same year, WSOR began operations over the Oregon to Fitchburg line, while the Evansville to Oregon segment remains out of service.  Today, WSOR operates the Reedsburg Subdivision between Madison and Reedsburg.  The 400 State Trail uses the former railroad between Reedsburg and Elroy; the Elroy-Sparta State Trail uses the former railroad between Elroy and Sparta; the La Crosse River State Trail uses the former railroad between Sparta and La Crosse; and the Great River State Trail uses the former line between Medary and Marshland.  


Located near Wisconsin Highway 71 southeast of Sparta , this stone arch bridge carries the former Chicago & North Western Railway over a farm driveway. In this area, the railroad skirted along the side of numerous large hills as it descended from Tunnel #3 into Sparta. Tall wooden trestles were initially used to cross the valleys between the hills. The first bridge at this location was one such timber pile trestle. In the late 1870s and early 1880s, the C&NW began upgrading this line, filling timber bridges and replacing them with stone and iron structures. In 1880, a stone arch bridge would be constructed at this location and the remaining trestle filled. The bridge consists of a standard 15-foot by 15-foot stone arch, constructed at a width of 120 feet. The bridge follows a standard C&NW design, using a semicircular arch and stepped wing walls which extend diagonally from the bridge. All four wing walls extend at an angle of 45-degrees. In addition, rubble stone was used to pave the floor of the structure. An unknown contractor constructed the bridge using stone quarried at an unknown location. A number of similar structures were constructed between Madison and Sparta, as the rugged terrain made stone arches and earthen fills the most cost effective solution. Stone arches were popular for railroad use, as they were durable and easy to construct. Since the initial construction, the bridge has seen few significant alterations. Currently, the bridge is used by the Elroy-Sparta State Trail. Overall, the bridge appears to be in fair to good condition, with minimal deterioration to the stone. The author has ranked this bridge as being locally significant, due to the size, age and common design.


Citations

Build date Chicago & North Western Valuation Notes at the Chicago & North Western Historical Society Archives
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele