UP WIS-32 Bridge (Racine)


Click the photo to view the full-size version

1/21
Date Taken:
Author:
Caption:

Name UP WIS-32 Bridge (Racine)
Chicago & North Western Railway Bridge #1498
Built By Chicago & North Western Railway
Currently Owned By Union Pacific Railroad
Superstructure Contractor Unknown
Substructure Contractor E&C Company of Milwaukee, Wisconsin
Length 228 Feet Total, 114 Foot Spans
Width 2 Tracks, 1 In Use
Height Above Ground 15 Feet (Estimated)
Superstructure Design Through Plate Girder
Substructure Design Concrete
Date Built 1959
Traffic Count 1 Train/Day (Estimated)
Current Status In Use
Chicago & North Western Railway Bridge Number 1498
Union Pacific Railroad Bridge Number 66.23
Significance Minimal Significance
Documentation Date 4/21/2024

In the early 1850s, several railroad companies began constructing railroad lines radiating from Chicago.  In 1855, the Chicago & Milwaukee Railroad (C&M) constructed a 45-mile railroad line, extending north from an existing railroad line at Ashland Avenue and Armitage Avenue in Chicago to the Wisconsin State Line near Kenosha.  At the same time, the Milwaukee & Chicago Railroad (M&C) constructed an additional 40 miles north to Milwaukee.  The two railroads would be consolidated into a new railroad known as the Chicago & Milwaukee Railroad (C&M) soon after completion, and would come under control of the Chicago & North Western Railway (C&NW) in 1866.  The C&M was leased to the Chicago, Milwaukee and North Western Railway (CM&NW) in 1883.  The C&NW acquired control of the CM&NW soon after.   The C&NW had constructed and acquired a large network of railroad lines through the Midwest.  This line formed a portion of the principal north mainline of the C&NW, eventually extending to northern Wisconsin and the Upper Peninsula of Michigan.  Due to increasing traffic along this line, a second track would be constructed between 1890 and 1892.

In the late 19th Century, railroad traffic had become a significant safety hazard for the City of Chicago.  A solution was devised to elevate the railroad tracks throughout the city, placing the railroads upon embankments and constructing subways at each street.  In 1898, the C&NW completed track elevation and a third track from Ashland Avenue to Balmoral Avenue; followed by Balmoral Avenue into Evanston between 1907 and 1910.  The C&NW would become a prominent railroad in the Midwest, eventually building a system over 11,000 miles long.  Throughout the 20th Century, this line would continue to be an integral part of the C&NW system.  The second track would be removed north of Kenosha after 1959.  In 1995, the C&NW would be purchased by the Union Pacific Railroad.  Union Pacific continues to operate the route as the Kenosha Subdivision.  Metra operates a commuter service, the Union Pacific-North Line over the Chicago to Kenosha section.


Located on the north side of Racine, this large through plate girder bridge carries the former Chicago & North Western Railway mainline over Wisconsin Highway 32 (Douglas Avenue). The first bridge at this location was constructed in 1896, and likely consisted of a through plate girder bridge. In 1912, the bridge was replaced by a 30-foot and a 34-foot through plate girder bridge, set onto concrete abutments and a steel pier. Due to the unusual geometry of the roadway below, a cost estimate for replacing the structure was first prepared in the mid-1930s, before being shelved. In 1952, the project was revisited and approved in 1958. Work on constructing a shoo-fly and utility relocations began in 1958, and contracts were awarded in early 1959. By June 1959, the present subway was completed. Currently, the bridge consists of two heavily skewed 114-foot double track through plate girder spans, set onto concrete substructures. The girders are heavily constructed, with two large plate girders, a ballast deck and curved and tapered girder ends. The abutments use a standard design, and the pier is constructed of two concrete columns. C.R. Myer & Sons was awarded the contract for the design of the bridge, while an unknown company fabricated the superstructure and E&C Company constructed the substructure. Through plate girder spans were commonly used by railroads, as they were durable and easy to construct. Since the initial construction, the bridge has seen few alterations, and one track remains in use today. Overall, the bridge appears to be in fair to good condition, with no significant deterioration noted. The author has ranked the bridge as being minimally significant, due to the common design.


Citations

Build date National Bridge Inventory (NBI)
Builder (substructure) Engineering News-Record; Volume 160, Issue 6
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele

Loading...