UP Armitage Avenue Bridge (East)


Click the photo to view the full-size version

1/11
Date Taken:
Author:
Caption:

Name UP Armitage Avenue Bridge (East)
Chicago & North Western Railway Bridge #1297
Built By Chicago & North Western Railway
Currently Owned By Union Pacific Railroad
Superstructure Contractor Lassig Bridge & Iron Works of Chicago
Substructure Contractor Unknown
Length 75 Feet Total, 43 Foot Main Span
Width 3 Tracks
Height Above Ground 13 Feet 10 Inches
Superstructure Design Through Plate Girder
Substructure Design Stone Masonry and Steel Bent
Date Built 1899
Traffic Count 75 Trains/Day (Estimated)
Current Status In Use
Chicago & North Western Railway Bridge Number 1297
Union Pacific Railroad Bridge Number 2.92
Significance Local Significance
Documentation Date 8/27/2022

In the early 1850s, several railroad companies began constructing railroad lines radiating from Chicago.  In 1855, the Chicago & Milwaukee Railroad (C&M) constructed a 45-mile railroad line, extending north from an existing railroad line at Ashland Avenue and Armitage Avenue in Chicago to the Wisconsin State Line near Kenosha.  At the same time, the Milwaukee & Chicago Railroad (M&C) constructed an additional 40 miles north to Milwaukee.  The two railroads would be consolidated into a new railroad known as the Chicago & Milwaukee Railroad (C&M) soon after completion, and would come under control of the Chicago & North Western Railway (C&NW) in 1866.  The C&M was leased to the Chicago, Milwaukee and North Western Railway (CM&NW) in 1883.  The C&NW acquired control of the CM&NW soon after.   The C&NW had constructed and acquired a large network of railroad lines through the Midwest.  This line formed a portion of the principal north mainline of the C&NW, eventually extending to northern Wisconsin and the Upper Peninsula of Michigan.  Due to increasing traffic along this line, a second track would be constructed between 1890 and 1892.

In the late 19th Century, railroad traffic had become a significant safety hazard for the City of Chicago.  A solution was devised to elevate the railroad tracks throughout the city, placing the railroads upon embankments and constructing subways at each street.  In 1898, the C&NW completed track elevation and a third track from Ashland Avenue to Balmoral Avenue; followed by Balmoral Avenue into Evanston between 1907 and 1910.  The C&NW would become a prominent railroad in the Midwest, eventually building a system over 11,000 miles long.  Throughout the 20th Century, this line would continue to be an integral part of the C&NW system.  The second track would be removed north of Kenosha after 1959.  In 1995, the C&NW would be purchased by the Union Pacific Railroad.  Union Pacific continues to operate the route as the Kenosha Subdivision.  Metra operates a commuter service, the Union Pacific-North Line over the Chicago to Kenosha section.


This bridge carries the Union Pacific North Line over Armitage Avenue west of Ashland Avenue in the Logan Square neighborhood of Chicago. During the late 19th Century, railroad traffic within the City of Chicago posed a serious hazard to the general population. Starting in the mid-1890s, the City of Chicago passed a number of ordinances mandating the elevation of tracks within the city. An ordinance was passed on December 27th, 1897 requiring the elevation of the Wisconsin Division of the C&NW between Sangamon Avenue and Wood Street, and the Milwaukee Division of the C&NW between the Wisconsin Division and Diversey Parkway. Construction began soon after, and was largely completed in 1899. This section required extensive retaining walls, which were constructed with stone.

Built in 1899, the bridge consists of a 43-foot and two 16-foot through plate girder spans, set onto steel bents and stone abutments. The bridge is set at a slight skew. The girder spans are typical for early track elevation projects, consisting of a traditional floor constructed of stringers and floorbeams, covered by a sheet metal deck. Grooves under the rails act as both a ballast channel and stringers, an unusual variation of the sheet metal deck design. In addition, the ends of the girders are a rounded taper, typical of C&NW bridges. The bridge was initially constructed for three tracks, although the westernmost track was removed in the 1980s. Lassig Bridge & Iron Works fabricated the girders for this track elevation project. This company fabricated numerous spans for the C&NW, and had its shop along this line at Wrightwood Avenue. However, the industrial lead into the Lassig shops was too sharp to allow the spans for this project to be shipped whole, and the pieces were instead assembled at the division shops before being installed. Stone for the abutments was quarried at a railroad owned quarry near Duck Creek, Wisconsin, and the abutments and retaining walls were constructed by contract.

This type of structure was initially popular for grade separations in Chicago, but fell out of favor as trough floor spans and concrete spans became more economical. The metal floor of this design of bridge was susceptible to pooling water, which would cause corrosion to the steel. In addition, the through girder design limited horizontal clearances on the bridge. While other bridges along this line have been replaced, it is not known when this bridge will be replaced. Overall, the bridge is in poor condition, with significant section loss and deterioration seen throughout the superstructure. The author has ranked this bridge as being locally significant, due to the common design.


Citations

Build date Chicago & North Western Railway Annual Report
Builder Missing Lassig Bridge & Iron Works plaque
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele

Loading...