Northern Pacific Railway Bridge #9


Click the photo to view the full-size version

1/76
Date Taken:
Author:
Caption:

Name Northern Pacific Railway Bridge #9
Built By Northern Pacific Railway
Currently Owned By City of Minneapolis
Superstructure Contractor (Original Trusses)
Superstructure Contractor (1923 Material)
Edge Moor Bridge Works of Wilmington, Delaware
American Bridge Company of New York
Superstructure Contractor (1923 Truss Strengthening) Minneapolis Steel & Machinery Company of Minneapolis, Minnesota
Substructure and Erection Contractor Frankman Brothers Construction Company of St. Paul, Minnesota
Engineer (Original Truss Design)
Engineer (1923 Bridge Design)
Charles Frederick Loweth
Frederick William Cappelen
Length 952 Feet Total, 247 Foot Main Spans
Width 2 Tracks
Height Above Ground 101 Feet
Superstructure Design Pratt deck truss and deck plate girder
Substructure Design Concrete
Date Built 1923, reusing trusses fabricated 1885
Traffic Count 0 Trains/Day (Bridge is a Trail)
Current Status Open to Trail Traffic
Northern Pacific Railway Bridge Number 9
Significance High Significance
Documentation Date 7/1/2012; 3/6/2016

In 1885, the Saint Paul and Northern Pacific Railway Company (StP&NP) began construction on five separate lines in Minneapolis. Line "A" would extend from Seventh Street in St. Paul to 20th Street in Minneapolis, crossing the Mississippi River twice. Line "B" would extend from St. Anthony Junction (near present day MN-280 and Kasota Avenue) to Northtown Junction. Line "C" would extend along Ramsey Street from Line "A" to Plymouth Avenue. Line "D" consisted of a 1 mile long industrial line along 2nd Street. Line "E" consisted of a connection between Line "A" and Line "C" along Mulberry Street. Work on the five lines would be completed in 1886.

The StP&NP would be purchased by the Northern Pacific Railway (NP) in 1896. NP continued to operate these lines as part of their vast Twin Cities network. Portions of line "C" would be abandoned in the 1960s. In 1970, NP would merge with rival Great Northern Railway and the Chicago, Burlington & Quincy to form Burlington Northern Railroad (BN). Line "E" would be abandoned during the 1970s. Portions of line "A" through downtown Minneapolis were removed during the 1980s, and Bridge #9 was purchased by the City of Minneapolis for trail use. In 1996, BN merged with the Atchison, Topeka & Santa Fe Railway to form BNSF Railway. BNSF currently owns line "A" and line "B" as part of the St. Paul Subdivision. The northern portions of Line "A" are also used by BNSF as a spur to serve the Cemstone plant. Lines "C" and "D" have largely been developed, and line "E" has become part of a trail.


Located between the 10th Avenue Bridge and the Washington Avenue Bridge, this unique deck truss bridge carries a pedestrian trail across the Mississippi River. The first bridge #9 featured a pair of 245-foot 8-panel pin connected Pratt deck trusses, approached by a deck plate girder viaduct of alternating 60-foot spans and 30-foot tower spans. The tower spans were reinforced with kingpost trusses, and the bridge bridge constructed of wrought iron. When constructed, the 30-foot truss panels were believed to have been longer than any previously constructed in the United States.

As railroad traffic increased and the University of Minnesota grew, a grade separation solution needed to maintain safe railroad operations. An order to depress the tracks through the area was issued in 1909, but the issue was not taken up by City Engineer Frederick William Cappelen until 1918. An agreement to relocate the tracks and construct a new bridge was reached in 1922. The new bridge would reuse the two trusses from the previous bridge. The old bridge was removed, and the trusses strengthened by Minneapolis Steel & Machinery Company. American Bridge Company fabricated third truss lines to add load capacity to the trusses, as well as five deck plate girder approach spans. Construction on the new bridge began in May 1922, and would be completed by December 1924. Frankman Brothers Construction Company constructed the substructures and erected the bridge.

When completed, the new double track bridge featured, from south to north, three 90-foot deck plate girder spans, the two deck truss spans, and an 85-foot and 80-foot deck plate girder span. The truss spans reused the stringers, floorbeams and trusses from the original 1885 bridge, and the pinholes were rebored during the strengthening. A riveted truss line was added to the middle of the 1885 trusses, which greatly increased the strength of the spans. The entire bridge was set onto concrete substructures, and an eight-degree curve was constructed in the south end of the bridge.

Reusing spans was not an uncommon practice for railroads. Often, old spans which did not have sufficient capacity for mainline use could be reused on branch lines. However, this bridge is an oddity, as the old bridge was reused in the successor. The remaining girder spans from the 1885 bridge were reused at various locations throughout Montana, where many still exist.

Overall, the bridge is in fair condition. Work has been ongoing since 2014 to stabilize the substructures, including repairing the existing concrete. The author is glad that the City of Minneapolis has chosen to rehabilitate this bridge and preserve it for years to come. The author has ranked this bridge as being highly significant, due to the unique reuse of the trusses.


Mississippi River Railroad Bridges

Upstream Display Minneapolis Western Bridge
Downstream Display Washington Avenue Bridge

Citations

Builders, build dates and relocation history Northern Pacific Railway Bridge No. 9 (Bridge 94246) Bridge Report
Railroad History Citation ICC Valuation Information, Compiled by Richard S. Steele

Loading...